27/05/2016

The Westminster Bridge Road project, in London, is continuing to progress successfully. We are in the 3rd month of works and seeing great progress to date.

Westminster Update 
Photo Source: McAleer & Rushe

The works at Westminster Bridge Road, for Marlin Developments, includes construction of new mixed used development comprising an apart-hotel building, 10-storey rear section and 7-storey wing at the front to Westminster Bridge Road, a restaurant, retail facilities and office suites at lower levels.
 
CHC are responsible for the Domestic, Public Health, LTHW and Ventilation and Sewage Pump Installations throughout the entire project.

CHC have been on-site from Mid-February and is envisaged to be fully completed and ready for handover January 2017.