Lesley Exchange Office Refurbishment

CHC Lesley exchange



Client: Lesley Exchange

Main Contractor: William Dowlling Limited

Completion: March 2008

Details:

CHC were appointed to undertake  upgrade works within Lesley Exchange, a 16,000sqm, 4 storey occupied office block in Belfast City Centre.

A detailed works programme was followed and involved:

  • A phased strip out and upgrade of mechanical services

  • Installation of natural gas services

  • Installation of new ductwork and air-conditioning system

  • New BMS control system

  • Low Pressure Hot Water system

  • New DDA compliant washrooms.

The success of this project arose from the implementation of a detailed disruption management plan was implemented by CHC to control the noise levels and dust during operational hours.  System changeovers were scheduled for the weekend to minimise health and safety risk and inconvenience.