Email
info@chcltd.com

Leeds Joint School Package

Kitchen Ventilation Works

Whitkirk

Client:  
Leeds City Council
Main Contractor:  CHC Group Ltd
Completion: September 2015

Details:
CHC Group Ltd have been appointed, by Leeds City Council, as the lead contractors, to complete Kitchen Ventilation Works at Wetherby St James Primary School and Whitkirk Primary School, which are fully operational schools.

The alterations of this project included the following; supply, erection, installation, connections, testing and commissioning of the whole of the electrical installations associated with the project.

The associated electrical installations associated with the project consisted of the following elements:
  • General lighting, emergency and external lighting circuits and associated luminaires alterations,
  • General power for kitchen ventilation,
  • Fire alarm modifications,
  • Security system modifications,
  • Earthing and bonding alterations,
  • Testing and Commissioning,
  • The production and provision of project manuals and “as fitted” drawings,
  • The provision of training to on site staff of the various included electrical systems,

We were able to complete all works, on both sites within the short timeframe available and on budget, all the while staying compliant with all regulations.